On May 23, it was learned from the Traffic Police Detachment of Yichang Public Security Bureau that in line with the municipal construction plan, Dalian Road (from the Yunji Tunnel exit to Lantai Road) will be renovated from June 9, which will last 184 days. Vehicles should plan the routing in advance based on the control time and schedule.
The renovation is divided into three phases. The first phase covers from June 9 to July 25, 46 days in total. The right-half road from the YunjiTunnel exit to Shantou Road is closed, while the left half is open to two-way traffic. The small tunnel on Dalian Road is still open to one-way traffic, only allowing vehicles to pass from Chengdong Avenue to Qingdao Road; Dalian road between intersections of Shantou Road and Beihai Road is fully closed for no entry.
The second phase covers from July 26 to Sep. 15, 52 days in total. The left-half road from the YunjiTunnel exit to Shantou Road is closed, while the right half is open to one-way traffic only in the same direction and reverse pass is prohibited; two-way traffic is restored on Dalian Road between intersections of Shantou Road and Beihai Road.
The third phase covers from Sep.16 to Dec.10, totaling 86 days. Partial reconstruction of Dalian Road will be carried out at intersections of Chengdong Avenue, Qingdao Road, Zhuhai Road, Shantou Road and Beihai Road. The specific construction plan and traffic control measures will be further noticed. (Reporter Pei Shujing, Correspondent Wu Jiangyun)