On Mar.18, the construction of Three Gorges International Cruise Center Wharf was busy but well-regulated. This project was undertaken by the Second Harbor Engineering Company. At present, the construction focus has been fully shifted from the aquatic pile foundation to the cast-in-place concrete beam system of the dock. By March 18, 160 aquatic pile foundations and 12 cast-in-place cross beams have been completed, achieving 60% of the overall progress.