On April 12, in the Yichang comprehensive bonded zoneproject site, tower crane waving, machinery roaring, taking advantage of the fine weather, workers are busy working. Up to now, 90% of the total work amount of Yichang comprehensive bonded zone phase I project has been completed , including 400,000 cubic meters of standard factory building, comprehensive and bondedbuilding, inspection warehouse, gate and other main projects have been completed. 40% of customs supervision facilitiesand information engineering has been completed. It is expected to be completed by the end of Julyand closed for operation within the year. (CorrespondentfromThree Gorges Daily:Yuan Da; Photographer:Luo Yixiang)